For the 2027 Simhastha, 12 new ghats are being built on the Godavari, ten in and around Nashik and two long ones on both banks at Trimbakeshwar, and the Kumbh Mela Authority has approved four bridge works in Nashik city. Most are due by March 2027, about four months before the first Amrit Snan on 2 August. In September 2026 most of the city’s Kumbh road and bridge works were about 30 per cent complete, the Free Press Journal reported.
The 12 new ghats
In March 2026 the authority’s commissioner, Shekhar Singh, set out the ghat plan, Punekar News reported. Nashik’s ghats go from 10 to 20, adding about 3.45 km of new ghats, built by the Nashik Municipal Corporation, the state infrastructure corporation (MSIDC) and the Water Resources Department. Each is planned with holding areas, separate entry and exit routes, police posts, watchtowers, changing rooms, sanitation and lighting.
| New ghat | Where | Length (as reported) |
|---|---|---|
| Kapila Sangam Ghat | Nashik | 400 m |
| Nandini Sangam Ghat | Nashik | 275 m |
| Takali Sangam Bridge Ghat | Nashik | 400 m |
| Takali Sangam Ghat | Nashik | 300 m |
| Nandur Dasak, left bank | Nashik | 500 m |
| Nandur Dasak, right bank | Nashik | 570 m |
| Odha Ghat | Nashik | 255 m |
| Someshwar Waterfall Ghat | Nashik | 174 m |
| Navashya Ganpati Ghat (moved to Anandavalli by a revised order) | Nashik | 167 m |
| Lakshminarayan Ghat | Nashik | 410 m |
| Left bank ghat | Trimbakeshwar | 1,614 m |
| Right bank ghat | Trimbakeshwar | 1,526 m |
The report put the ten Nashik ghats at ₹361.26 crore. For Trimbakeshwar, the authority’s own order of 7 October 2025 approves ₹177.86 crore for the new ghats and related works on both banks, to be built by the Water Resources Department by the end of March 2027. Our page on the Godavari ghats of Nashik shows where each ghat sits in the authority’s plan.
The bridges in Nashik city
On 14 September 2025 the authority approved four bridge works by the Nashik Municipal Corporation, for ₹62.80 crore in all. On 3 October 2025 it cancelled one, a new bridge beside the existing one over the Waldevi river at Vadner Dumala, and approved a new bridge on Trimbak Road in its place. All four are due by March 2027.
| Bridge work | Approved | Due |
|---|---|---|
| New bridge on the 24 m DP road over the Nandini river at Milind Nagar, to ease traffic | ₹19.23 crore | March 2027 |
| A bridge parallel to the existing one near the Lakshminarayan temple | ₹20.96 crore | March 2027 |
| A down ramp next to the Sant Gadge Maharaj bridge | ₹5.85 crore | March 2027 |
| New bridge on Trimbak Road over the Nandini at Pimpalgaon Bahula, replacing an old narrow bridge | ₹11.51 crore | March 2027 |
On 1 September 2026 the Free Press Journal reported that the municipal corporation was handling 28 road and 7 bridge projects over the Godavari and its tributaries, worth about ₹1,400 crore. Most were about 30 per cent complete. The Milind Nagar bridge over the Nandini, also called the Nasardi, was the furthest ahead at about 45 per cent. Municipal officials blamed approvals that came in phases.
Going to the Nashik Simhastha 2027? Tirth.com can plan it for you. We are taking bookings for the Kumbh, with packages, our own people on the ground and help from your first call to the bath. Leave your number and our yatra team will call you back.
- Stay and travel planned around your bathing day
- Our own people on the ground at the mela
- No payment to enquire
Calls between 10:30 am and 7:30 pm IST, usually the same working day.
From Tirth.com, which runs this guide · How this works
Deadlines, and the work at Ramkund
At a review on 19 July 2026, Minister Girish Mahajan told the authority that all Simhastha works in Nashik and Trimbakeshwar must be finished by March 2027, the Free Press Journal reported. The ghats he reviewed included those near the Godavari and Kapila confluence, at Takli, at Odha, at Dasak and on both banks at Trimbakeshwar.
Work is also going on at the old centre. On 14 October 2026 the Free Press Journal reported that a new ghat with new stone steps had been completed at Ramkund and that nearby ghats were being repaired. To finish paving and other work before the flag hoisting on 31 October 2026, the administration said it would close the riverfront between the Ahilyabai Holkar bridge and the Talkuteshwar temple to devotees for 15 to 20 days, with dashakriya rites continuing at set spots. See our flag hoisting page for that day.
Photo: Mahi29, CC BY-SA 4.0, via Wikimedia CommonsWhat is not announced
- Which new ghats will open to the public, and from when.
- Whether the new bridges will carry vehicles or only people on bathing days.
- An official statement that any of these works is complete.
For the dates and the wider plan, start with the Nashik Kumbh guide, and read how to read Nashik Kumbh 2027 updates to judge each new report.
Plan your trip
Sources
10 sources · checked 16 Oct 2026
- Simhastha 2027: 12 New Ghats to Come Up Along Godavari in Nashik and Trimbakeshwar · Punekar News ·
- Administrative approval order for 'Trimbakeshwar ghats and bandhare': new ghats on both banks of the Godavari at Trimbakeshwar (Rs 177.86 crore) · Nashik–Trimbakeshwar Kumbh Mela Authority, Government of Maharashtra ·
- Administrative approval order for bridges and ancillary works in the Nashik Municipal Corporation area (4 works, Rs 62.80 crore) · Nashik–Trimbakeshwar Kumbh Mela Authority, Government of Maharashtra ·
- Revised administrative approval order: Vadner Dumala bridge cancelled; new bridge on Trimbak Road over the Nandini at Pimpalgaon Bahula · Nashik–Trimbakeshwar Kumbh Mela Authority, Government of Maharashtra ·
- Nashik: 70% Work Pending On 35 Major Kumbh Road, Bridge Projects; March 2027 Deadline Nears · Free Press Journal ·
- Nashik: Girish Mahajan Sets March 2027 Deadline For Simhastha Ghats And Infrastructure Works · Free Press Journal ·
- Nashik: Ramkund, Nearby Ghats To Remain Closed For 15–20 Days Ahead Of Simhastha Ceremony · Free Press Journal ·
- Administrative Approvals: ghat, temple, tank and forest works (Nashik–Trimbakeshwar Simhastha Kumbh Mela) · Nashik–Trimbakeshwar Kumbh Mela Authority, Office of the Divisional Commissioner, Nashik, Government of Maharashtra ·
- Administrative Approvals: Nashik–Trimbakeshwar Simhastha Kumbh Mela · Divisional Commissioner Office, Nashik, Government of Maharashtra ·
- Kumbh Mela Plan (First Edition): Nashik–Trimbakeshwar Simhastha Kumbh Mela 2027 · Nashik–Trimbakeshwar Kumbh Mela Authority, Office of the Divisional Commissioner, Nashik, Government of Maharashtra ·
Photo: Rohit R Nashik, CC BY-SA 4.0